To
download this factsheet on hydro power in
pdf format please click here
Introduction
Hydroelectricity
is the conversion of energy from flowing
water into its more useful form –
electricity. Flowing water turns a
turbine, which in turn converts this
energy to electricity. Where traditional
water wheels use the power of falling
water to work milling equipment, modern
hydro-turbines use this power to create
electricity.
A
good micro-hydro scheme will be designed
to operate with minimal environmental
impact with a degree of automatic control
to offer low running costs and high
reliability over a long life. The
‘power’ available in a river relates
directly to the work done by the weight of
water as it falls through a vertical
distance under the acceleration of gravity
– i.e. a function of the product of
‘head’ and ‘flow’. The
‘electrical’ power output has to take
regard of the efficiencies of the turbine
and generator.
1.
Head
The
‘head’ is the vertical distance that
the water falls on the available section
of waterway, measured in metres. This can
be worked out by looking at OS maps,
measuring with a board and spirit level,
or using a surveyor’s theodolite. It is
also worth considering if you can
co-operate with neighbouring landowners to
access additional height.

Figure
1
:
Typical Site with Low Head Potential
2.
Flow
The
gross annual flow in a river is the
product of the size of the catchment x the
annual rainfall less any water that is
removed from the catchment by way of
evaporation, transpiration, or by
agricultural or Industrial abstractions. A
certain minimum volume of water, known as
the ‘residual flow’ must be left in
the river to protect the ecology of the
river species. The flow potentially
available for hydropower is that left
after all other priorities are satisfied.
Since rainfall is
seasonal,
the daily flow rate should be recorded
over 12 months to determine the ‘Flow
Distribution Curve’ and the ‘mean
annual flow’ (m3/s) for the
proposed site. The Environment Agency will
state what residual flow must be left and
authorise what flow can be used for
hydropower.
3.
Assessing a site for micro-hydro potential
Micro-hydro
schemes are generally classified as either
– high or low head sites. Low head sites
will include old mills and weirs, with a
head of around 1-4m. To achieve a
reasonable power output either the
‘head’ or the ‘flow’ needs to be
of significant value. Of the two, a high
head is preferred as it is more likely to
offer a shorter payback period. Low head
sites, particularly where there is some
existing civil infrastructure, can still
offer a good return if a large enough flow
is present. High head sites will typically
be steep fast flowing upland streams and
rivers, where though the flow is low a
high head can easily be achieved. These
sites will generally be without any
previous hydropower development but are
still well worth investigating.
‘Best
Practice’ dictates that designs without
stored water (i.e. dams) should be based
on the lowest flow parameters – a
turbine designed to accommodate large
winter flow rates (expensive) may
otherwise lie idle for months with
insufficient water to operate it in the
summer. Designing for low summer flow
rates will require a smaller, cheaper,
turbine that is more likely to operate for
most of the year.
To
determine a ‘first estimate’ of the
potential electrical power available for a
site you need to use summer flow figures
and apply the formula: Power (kW) = 5 x
Head (m) x Flow (m3/s).
Multiplying this answer by the number of
hours this flow is available during the
year will give an indication of the annual
energy output in kWh.
The
‘first estimate’ figure should allow a
potential developer to decide whether to
continue with further investigation or
not. There is no hard and fast rule of
what size site is economically viable.
Generally the cost of an ‘Abstraction
Licence’ and ‘Land drainage
Consents’ are similar irrespective of
site size, so the cost to the smaller site
is disproportionately large.
However a remote off grid site may
find it cheaper to go through the
licensing process than pay for a grid
connection.
Also the costs of employing a
professional hydro engineering company may
make the smaller site prohibitively
expensive. Generally sites with above
10kW-installed capacity may be economic
for professional development.
Sites
below 2kW installed capacity may be
suitable for DIY. Sites between 2 –10kW
pose a difficulty, as there may be enough
flow to be potentially dangerous if a weir
were to fail and cause a risk of flooding
downstream yet may not generate enough
value to justify the use of professional
consultants. Great care needs be exercised
if considering a DIY scheme.
In
addition to information about micro-hydro
sites on Dartmoor, the ‘Dartmoor
Hydropower Survey’ produced by DARE
contains a wealth of generic information
about hydro power that is applicable
anywhere.

Figure
2
:
More Low Head Potential
4.
Environmental issues
All
hydro schemes have an environmental
impact. Water is abstracted from the main
stream and diverted through a turbine
before being returned to the main flow.
During this stretch the flow in the main
stream is depleted which could adversely
affect bio-diversity – because of this
the amount of flow that can be taken from
the flow will be regulated in order to
leave an acceptable base ‘residual’
flow level. The Environment Agency has a
statutory duty to maintain the health of
the river and protect the interests of
existing lawful water users. Any hydro
scheme will need to hold an ‘Abstraction
Licence’, controlled by the nearest
Government Office of the South West –
such licenses could take up to 6 months to
get.
Turbines
are not ‘fish friendly’ so adequate
screening both up and down stream has to
be provided to stop fish and fry entering
the turbine. Where migratory fish exist in
a river, a fish ladder must be installed
to enable fish to complete their journey
upstream. However a well-designed hydro
scheme will mitigate any environment
damage caused during construction and over
time will generate ‘clean’ energy for
many years.
5.
Grid connection
Micro-hydro
systems can be grid connected or
stand-alone. In an off grid system the
power is used to charge a bank of
batteries to collect the power, meaning
that power will always be available. A
back up generator might also be necessary
for installations like these, to provide
emergency cover to back up for seasonal
variations in water flow. The batteries
can be used to power low voltage DC
appliances, or used with an inverter to
convert the power to more conventional 240
volt alternating current (AC). A charge
controller is also required in order to
ensure that the batteries are not over
charged, and when the batteries are full
to divert electricity to other useful
sources such as space or water heaters.
In
sites that are connected to the grid the
power will be fed through an inverter back
into the grid, and a two way meter will
measure power exported to the grid, and
power imported from the grid. If the
scheme produces more electricity than a
site uses, then substantial profits can be
made by selling back into the grid, and
this will further help the economics of a
site.
6.
Costs
Considerable
micro-hydro potential exists in many hilly
areas. The initial costs will be quite
high, but with hydro sites having the
potential to run indefinitely, they
represent a medium to long-term investment
that can prove very cost effective. Sites
will require periodic component
replacements, e.g. a new generator every
10-15 years and new turbine approximately
every 25 years, but with this maintenance
they can produce clean, green electricity
indefinitely. This electricity can then be
used, offsetting the cost of buying in
electrical power, and any excess power can
be sold back into the grid, often
generating significant incomes – all
this helps offset the cost of
installations and pay back the original
investment.
Micro-hydro
costs are very site specific, and can vary
between £1000-£4500 per installed kW
subject to the amount of civil engineering
required. A 10 kW site may cost between £10,000
and £45,000 to develop, but if available
for 8000 hours per annum could generate
80,000 kWh. At a sale price of 6p/kWh this
would equate to an income of about £4800
per year, or offset a substantial amount
of ‘bought in’ electricity. In
addition such a scheme would (at the time
of writing – January 2005) qualify to
sell ‘Renewable Obligation
Certificates’ (ROC’s) (80 x £30 = £2400)
offering a possible combined income of £7200/yr.
In this example a scheme could pay for
itself in 6.25 years.
|